Project Updates:
Baseball Field:
- Replacement of natural grass with artificial turf in the foul ball area complete.
- Replacement of windscreen on fencing in progress.
Softball Field: In progress . . .
- Install artificial turf, with the outfield remaining natural grass.
- Pour concrete pads for new bleachers and two storage containers.
- Replace deteriorated wood on the backstop.
- General maintenance items, such as electrical and fencing improvements.
Anticipated Completion: Late February